Wallonia halts work on Google data center over revoked permit
The dispute involves a switch to river-water cooling. Google is challenging the permit revocation, with a public hearing set for 7 January.

Google has been told to suspend construction of its Belgian data center near Charleroi by the Walloon Region, following months of building without a valid permit. The order affects a site across Farciennes and Aiseau-Presles and follows Greenpeace Belgium’s request for regional intervention.
The project initially received permission in 2024 for three air-cooled data centers. Greenpeace said Google changed the design in 2025 to combine two buildings into a larger one and use Sambre river water for cooling instead of air.
The amended permit won administrative approval in April 2026. Infrastructure minister François Desquesnes subsequently withdrew it in August after residents appealed. Desquesnes said the application involved taking 600 cubic metres of river water an hour; according to Belga, less than a quarter would have flowed back.
Reports from residents that building had continued prompted Greenpeace to examine satellite images and initiate an emergency procedure. Raphael Stokis, a Walloon official, told Belgian broadcaster VRT that roughly 300 construction workers were at the location when the stop order was issued.
VRT reported that Google proceeded with construction while contesting the revocation. The company sought suspension and annulment of the minister’s decision at Belgium’s Council of State on 17 October. On 16 November, Greenpeace and several residents requested to join the proceedings; the public hearing is scheduled for 7 January.
A Google spokesperson told VRT that the company is committed to discussing its Wallonia investments openly and collaboratively with the regional government and experts.